What's The Duration Of An Average Kitchen Remodel?

If you're planning a kitchen renovation, one of the first questions you probably have is, "How long is this going to take?" Kitchen remodels involve multiple stages, from initial demolition to the final walkthrough. And depending on the scale of the project, the timeline can vary quite a bit.

Read on to learn typical timelines for minor updates, major remodels, and kitchen expansions so you can set realistic expectations.

Key Stages of a Kitchen Remodel

Every kitchen renovation follows a similar workflow that includes planning, demolition, construction, and completion stages. The scope and specifics of your project will determine how long each phase takes.

how long does it take to renovate a kitchen

Planning and Design

The planning and design process involves creating initial layouts, selecting finishes like cabinetry and countertops, and getting required permits. This upfront stage takes approximately 2-4 weeks.

Key steps include:

Proper planning prevents delays later on. So don't rush this important stage!

Demolition

With the design solidified, it's time for demolition. This involves gutting the existing kitchen layout to prepare for new construction and remodeling.

The demolition crew will be responsible for:

Demolition typically takes 1-2 days depending on the scope of work. The space will be stripped back to the framing so new infrastructure can be added.

Construction and Installation

The lengthy construction phase involves building out the new kitchen based on plans. Timelines here vary drastically depending on project size.

Some of the key activities include:

A smooth construction workflow depends on coordination between the various tradespeople like plumbers, electricians, tilers, carpenters, and countertop fabricators.

Inspection and Completion

The final phase includes thorough inspection along with any repairs, cleanups, or touchups required after the technical reviews. Expect 1-2 weeks here for the final finishing touches.

It's critical homeowners do a walkthrough at this stage to:

What Impacts Kitchen Remodel Duration?

Many factors influence the timeline for remodeling a kitchen. Here are some of the key considerations:

Scope of Work

The extent of renovations and upgrades you're doing is a major variable. Are you fully gutting and expanding the space or doing a simpler replace-in-place remodel? Structural changes like knocking down walls takes more coordination.

The size of the kitchen itself also matters. Larger kitchens require more materials, labor, demolition, construction, etc. So naturally, they take longer from start to finish.

Design Selections

Custom elements like cabinetry, tilework, and lighting fixtures require extra fabrication time. If you import more unique finishes from specialty suppliers, that can extend lead times as well.

Creating an elaborate or luxury kitchen typically prolongs the schedule compared to simple, stock designs.

Unforeseen Issues

No matter how carefully you plan, unexpected problems can come up like discovering water damage behind walls or challenges rerouting plumbing. These incidents can delay projects weeks or even months in some cases.

It's wise to budget extra time for contingencies in case anything comes up. The contractor may also charge more for extensive unanticipated repairs.

Typical Kitchen Remodel Timelines

Understanding average durations for different remodeling scenarios helps you plan more accurately.

Minor Kitchen Update

A minor update involves replacing cabinet doors, hardware, lighting, and backslash plus new paint or countertops. Cosmetic-only updates average 4-6 weeks.

Major Kitchen Remodel

Gutting and fully renovating the kitchen falls into this category. You can expect 6-9+ weeks for construction depending on kitchen size and chosen finishes.

Adding Square Footage

Expanding a kitchen or reconfiguring the layout for an open concept often requires adjustments to walls, floorplans, and infrastructure. 2-3+ months isn't unusual for larger remodeling projects involving construction.

Working With Contractors

Hiring experienced contractors for your kitchen remodel comes with a few time-saving perks:

Plus contractors have established supply chain contacts which can minimize material shortages. All of this equates to likely finishing more quickly.

Key Takeaways

Most minor kitchen updates with stock components require 4-6 weeks. Extensive remodels involving demolition and custom elements range from 6-9+ weeks on average. Expanding square footage can lengthen timeframes to 2-3+ months.

The scale of upgrades, design choices, potential issues arising, and crew experience all impact duration. Build contingencies into your plan since unforeseen circumstances can certainly delay projects.

Carefully weighing your kitchen remodel options and goals makes it easier to estimate a realistic schedule. And an organized, communicative contractor keeps things running on time!

Supply Chain Disruptions

Global events like the COVID-19 pandemic have severely disrupted product and material supply chains. Shortages and delivery delays are still common across industries like construction and home improvement.

Many key kitchen renovation materials are imported like certain cabinetry, countertops, tiles, and high-end appliances. So supply issues often impact these long-lead items, prolonging timelines weeks or months until orders arrive.

It's wise for homeowners and contractors to order products early and confirm dates to prevent holdups. Having backup material options helps too if preferred brands remain unavailable or severely backlogged.

Customization Requests

Personalized kitchen features absolutely add character plus increased functionality in many cases. However, custom cabinetry, countertops, tilework, etc. tack on extra fabrication and installation time versus stock solutions.

Special order appliances also take longer to source and deliver to job sites. So extra customization equals more calendar days from demolition to completion typically.

Build in some flex room if opting for bespoke kitchen elements rather than premade offerings. Under promise and over deliver to clients!

Change Orders

It's common for homeowners to modify kitchen plans with change orders once demolition begins. Visually seeing the blank canvas often sparks new spatial ideas or different aesthetic visions.

While enhancing overall outcomes, these 11th-hour tweaks disrupt the smooth flow of construction. Change orders may require reworking plans, securing additional permits, reordering materials, etc.

They also have cascading effects resulting in subcontractor delays down the line. So weigh alterations carefully or risk tacking on weeks to your remodeling timeline.

Permitting Delays

Local permitting and inspections ensure kitchen remodels comply with building codes and standards. But unfortunately, the approval process itself tends to drag out projects.

Backlogs from busy construction seasons mean contractors must wait longer for permit submissions to get reviewed. And if plans require revisions, additional lag time results.

Closing permits once inspections occur suffers similar sluggishness - a finalized kitchen can sit lingering weeks! Streamlining this paperwork and administrative stage would accelerate remodeling jobs.

The home improvement industry continues struggling with chronic worker shortages, especially skilled tradespeople like electricians, framers, and plumbers. These labor constraints slow each construction phase.

Fewer crews and tradespeople mean juggling more kitchen remodels simultaneously. So manpower access limitations hinder turnaround times project to project right now.

Labor scarcity shows no signs of abating either. Constructing an in-law suite or expanding a kitchen may require getting in line for months before breaking ground in many regions.